Thiruvananthapuram, Nov 26 The 400-kV Udupi-Karinthalam double-circuit interstate power transmission line, expected to ease the long-standing electricity transmission constraints in north Keralam, will soon undergo test charging, the KSEB said on Thursday.
In a statement, the Kerala State Electricity Board (KSEB) said the construction of the transmission line from the Udupi power station in Karnataka to Karinthalam in Kasaragod district has been completed.
KSEB said that the line will undergo test charging on Friday.
At present, electricity demand in the Kasaragod and Kannur districts and in the northern parts of Kozhikode is mainly met by the Areekode-Kanjikode-Mylatti 220-kV double-circuit line and the Kakkayam-Mundayad 110-kV double-circuit line, officials said.
The North Malabar region requires around 900 MW of power, but the existing transmission network can carry only about 600 MW.
A portion of Kasaragod district’s power requirement is also met through a relatively low-capacity 110-kV transmission line from Karnataka.
The high load on existing lines makes it difficult to even shut them down for maintenance. Disruptions in power supply from Karnataka have also led to situations where electricity restrictions had to be imposed, the KSEB said.
Once fully commissioned, the new 400-kV line will enable the transmission of more electricity from Karnataka’s national grid to north Keralam, officials said.
It will increase the region’s power transfer capacity, reduce the excessive load on existing 220-kV lines, and improve the reliability of the transmission network.
The project is also expected to support the industrial and commercial development of Kasaragod and Kannur districts, officials said.
Udupi Kasargod Transmission Limited (UKTL) undertook and completed the construction of the 400-kV transmission line and the 400-kV gas-insulated switchgear (GIS) substation at Karinthalam through the Central Electricity Authority’s tariff-based competitive bidding process, KSEB said.
Two 500-MVA, 400/220-kV transformers have been installed at the substation.
The KSEB has also completed construction of the associated 220-kV multi-circuit transmission line, including a line-in-line-out (LILO) arrangement, to carry power from the new Karinthalam substation to various areas, officials said.
The Kasaragod-Mylatti, Kasaragod-Kanjikode, Kasaragod-Taliparamba and Kasaragod-Ambalathara 220-kV transmission lines are also ready for energisation, they said.
With the commissioning of the expanded network, Keralam’s power import capacity is expected to rise from 4,445 MW to 5,105 MW, the KSEB said.
The ongoing construction of the Karinthalam-Wayanad 400-kV transmission line and the 400-kV GIS substation at Payyampally in Wayanad will further strengthen the power transmission system in north Keralam.
Once these projects are completed, a robust 400-kV transmission corridor connecting the southern and northern ends of the state will be in place, KSEB said.
It will facilitate high-capacity power transfer between different regions and help meet rising electricity demand while ensuring grid reliability and stability, KSEB added.
(PTI News)